Nu Energy Peaker Power Station

JLE were contracted by Nu Energy to install the electrical power and control for 2 x GE LM 600’s Gas fired turbines.

Services
Instrumentation
,
Mechanical
,
Electrical
,
Location
New Plymouth, New Zealand
Client
Nu Energy
Project team size
20
Project duration
6 months

This included installing 60,000m of cable in underground ducting and terminations suitable for a hazardous area. JLE installed, terminated and provided quality assurance for all LV cabling, fibre optics and control cabling for the project and balance of plant. This included water treatment facilities, gas reticulation infrastructure, plant amenities infrastructure, and oil filtration skids. JLE Mechanical resources were also involved with the pre-commissioning of GE turbines. This was a fast tracked project.