About Hero

Waingongoro Pipe Bridge Replacement

JLE were awarded the contract to supply and install the replacement stainless steel pipework to span the new bridge built by Downer.

Services
Mechanical
,
Fabrication
,
Location
Taranaki, New Zealand
Client
Downer NZ
Project team size
5
Project duration
4 months

This involved the workshop fabrication, spooling, site installation, pressure testing and commissioning. The project was completed with zero LTI’s.

Features
No items found.
No items found.
No items found.
Get in touch

Contact us to discuss how JLE can support your next industrial build.

Contact Us
CTA Banner