EV Car Charger Installation
JLE were engaged to install 9x EV chargers on the Fonterra Whareroa site. This included significant civil management, design support, Electrical underground ducting, Installation of new switchboard and connection of chargers, termination drawings and mechanical support from the JLE Mechanical team.
Services
Electrical
,
Fabrication
,
Location
Hawera, Taranaki, New Zealand
Client
Fonterra
Project team size
4
Project duration
5 months
The specific charger in this article is a Schneider EVlink 22.1kw unit.
JLE also service and test pre-installed chargers with the use of our certified test equipment.
Power capacity checks can be carried out to determine if the onsite electrical system can withstand the charging load to ensure that upstream circuit tripping does not occur.
Features
Get in touch
Contact us to discuss how JLE can support your next industrial build.
Contact Us