Waingongoro Pipe Bridge Replacement

JLE were awarded the contract to supply and install the replacement stainless steel pipework to span the new bridge built by Downer. This involved the workshop fabrication, spooling, site installation, pressure testing and commissioning. The project was completed with zero LTI’s.

Services
No items found.
Location
Taranaki, New Zealand
Client
Downer NZ
Project team size
5
Project duration
4 months