Client: Puma Energy
Size of Project Team: 4
Project Duration: 6 months
Lost Time Injuries:0
Project Description
JLE was contracted to undertake hazardous area electrical upgrade work at Puma Energy’s Kimbe fuel terminal in PNG. The work included supply and installation of power & control cabling, junction boxes, local control stations, emergency stop buttons, cable ladder, in-ground ducting, switchboard modifications, variable speed drives, and soft starters. The work was carried out by our qualified hazardous area electricians from NZ with assistance from our PNG national staff.