Client: Robt. Stones
Project Value: $2,000,000.00
Size of Project Team: Twenty
Project Duration: Twelve Months
Lost Time Injuries:0

Project Description
Completion of Instrumentation and Electrical carry-over work on the FPSO Umuroa. JLE’s involvement in this project started in the Kepel Shipyards with scoping and work package development. JLE then supplied twenty electricians, instrumentation technicians and two automation engineers to complete all carryover work while the FPSO Umuroa was anchored 52km off the coast of Taranaki over the Tui Oil Field. The carry-over project lasted twelve months; JLE continues to provide offshore personnel to OMV & Modec off the coast of Taranaki. JLE’s ongoing commitment to safety delivered a project with zero LTI’s and MTI’s.