JLE was awarded the contract to supply the electrical and instrumentation works for the Ruakaka Water Treatment Plant project. The contract included hooking up the mixers while also supplying, installing and commissioning the VSD’s, instruments and distribution boards.
JLE helped contribute to a project that was completed on-time, within budget and with zero LTI’s.
| Client | Robt Stone & Co. Ltd |
|---|---|
| Location | Whangarei |
| Project Value | $200,000 |
| Size of Project Team | |
| Project Duration | 11 |
| Lost Time Injuries | |
| Completion | 2012 |