Completion of Instrumentation and Electrical carry over work on the FPSO Umuroa. JLE’s involve-ment in this project started in the Kepel Shipyards with scoping and work package development. JLE then supplied twenty electricians, instrumentation technicians and two automation engineers to complete all carryover work while the FPSO Umuroa was anchored 52km off the coast of Taranaki over the Tui Oil Field.
The carryover project lasted twelve months; we now supply four maintenance staff to FPSO’s and the Wellhead Platforms off the coast of Taranaki. JLE’s ongoing commitment to safety delivered a project with zero LTI’s and MTI’s.
| Client | Robt. Stones |
|---|---|
| Location | Umuroa |
| Project Value | $2,000,000.00 |
| Size of Project Team | 20 |
| Project Duration | 12 months |
| Lost Time Injuries | |
| Completion | 2012 |